Method of operation
All the checks on the checklist, created during the preceding activity, are gone through. This determines
whether the test environment, test tool and workplace function and whether they meet the previously set requirements.
Any missing parts are reported to the stakeholders by means of a defects report. These parts should of course then be
made available as quickly as possible. Missing parts in the test environment will have a delaying effect and have an
impact on the entire project. The Execution phase is often on the critical path, and if it cannot start (because for
example the test environment is not functioning), the entire project will be delayed. The intake should not be
underestimated, and should be carried out as quickly as possible. The intake of the test environment is preferably
carried out during the Specification phase. If this is not possible, then it should be done at the start of the
Execution phase, at the latest. This may be the case if the test object is required and is only available at that time.
Products
-
Defects
-
Operational and usable workplace
-
Operational and usable test environment
-
Operational and usable test tool
-
Intake report
Tools
-
Testware management tool
-
Defect management tool
|